What is the minimum curing period?

DWQA QuestionsCategory: Civil EngineeringWhat is the minimum curing period?
Editor Staff asked 9 months ago

What is the minimum curing period?

1 Answers
Editor Staff answered 9 months ago

IS 456 – 2000 recommends that curing duration of concrete must be at least 7 days in case of Ordinary Portland Cement, at least 10 days for concrete with Mineral admixtures. It also recommends that the curing duration should not be less than 10 days for concrete of OPC exposed to dry and hot weather conditions and 14 days for concrete with mineral admixtures in hot and dry weather.